Project management requires organization, standardization and visibility. When a company starts to deal with several initiatives at the same time, relying on manual processes can lead to rework, lack of control and difficulty in tracking the actual progress of each project.
Within Smartsheet, it is possible to structure a PMO with a flow for receiving initiatives, approval, automatic project creation, schedule monitoring, budget management and updated dashboards. This model helps to centralize information and make the process more efficient from start to finish.
How We Created a Complete PMO on Smartsheet | Project Management in Practice with TaskIT – YouTube
Macro view of initiatives
The process begins with a macro view of all initiatives received. In a dashboard, you can view general data on everything that has already been sent, approved or not approved.
This panel works as a monitoring center, allowing the team to have clarity about the volume of initiatives, the status of each one and the most important information for decision making.
In addition, the process has an initiative intake form. It is through this that a new project request is sent for evaluation.
Intake of initiatives: standardizing the receipt of projects
Intake of initiatives is an important step to standardize the entry of new projects. Instead of receiving demands through different channels or formats, the form centralizes the information necessary to start the analysis.
When you send a new initiative, it automatically appears in the spreadsheet of received initiatives. This spreadsheet does not yet represent the projects created, but rather all the requests that entered the flow.
From there, the initiative goes through an approval process within Smartsheet.
Approval flow within Smartsheet
After an initiative is sent, the flow requests the update of important information, such as the requested budget and the coordinator’s analysis.
These requests can arrive via notification within Smartsheet and also via email, making it easier for those responsible to monitor them.
After the initial analysis, the initiative goes to the VP for approval. The person responsible receives the main project data and can approve or disapprove the request.
If the initiative is rejected, the flow requests a justification. If approved, this approval becomes the trigger for the automatic creation of the project.
Automatic project creation with Control Center
Once the initiative is approved, Smartsheet Control Center takes action to create a new project folder based on a previously configured template.
This model ensures that all projects follow the same standard, preventing the team from having to manually create structures every time a new initiative is approved.
The template folder may contain, for example:
- Project management;
- Project tasks;
- Gantt schedule;
- Pre-configured dependencies;
- Budget management;
- Project dashboard.
As a result, each new project comes with an organized structure ready for monitoring.
Using a blueprint for standardization
For Control Center to be able to automatically create projects, it is necessary to configure a specific blueprint.
It is within the blueprint that points such as:
- Which model will be used;
- In which workspace the project will be created;
- What data will be sought;
- What information will be returned to the macro view.
This configuration allows the projects created to follow a standard and maintain connection with the general information monitored by the PMO.
Summary: information updated in real time
When a project is created, its main information is stored in the summary.
The summary pulls data directly from the project folder and allows metrics to be updated in real time. This is important because the received initiatives spreadsheet is not the place where ongoing project information is changed.
With the summary, the PMO can monitor updated project data without relying on manual filling in different places.
Gantt schedule and dependencies
Each project created can come with dates and dependencies already configured. This makes it easier to view the schedule and helps you understand the relationship between tasks.
In the Gantt view, the team can track project dates, visualize dependencies and identify the critical path.
This structure makes monitoring clearer, especially in projects that follow a logical sequence of execution.
Integrated budget management
In addition to task and schedule management, the model can also include budget management.
In this structure, the approved budget is recorded and the realized budget can be updated as expenses occur. From this, the balance is calculated based on the difference between the approved budget and the amount already realized.
This connection between project management and budget management allows you to monitor not only the progress of activities, but also the financial control of the initiative.
Macro and micro dashboards
The PMO in Smartsheet can have two levels of dashboards.
The macro dashboard presents an overview of initiatives and projects, allowing you to monitor the portfolio as a whole.
The micro dashboard shows specific data for each project created, including progress information, budget, dates, status and responsible parties.
With this, the team is able to navigate between an executive vision and a detailed vision, according to the need.
Benefits of a PMO on Smartsheet
Structuring a PMO within Smartsheet helps bring more control, standardization and automation to initiative management.
Among the main benefits are:
- Standardized receipt of initiatives;
- Structured approval process;
- Automatic creation of projects;
- Use of models with pre-configured tasks and dependencies;
- Budget monitoring;
- Updated dashboards;
- Macro view of all initiatives;
- Reduction of manual work when creating new projects.
This type of structure is especially useful when projects follow a similar pattern. Instead of recreating everything from scratch with each new demand, the team now relies on an automated and organized flow.
Conclusion
A PMO within Smartsheet allows you to centralize the receipt of initiatives, automate approvals, create projects based on models and monitor indicators in real time.
With resources such as forms, approvals, Control Center, blueprints, summaries, Gantt, budget management and dashboards, the company gains more visibility and efficiency in managing its projects.
This model helps reduce manual processes, maintain standardization and ensure that each approved initiative starts with a structure ready for execution and monitoring.